Pan London SECURE CHILDREN’S HOME

Next Steps

Thank you for visiting our website.  Please leave us your feedback using the online feedback form.  
 
We were planning to run a second round of consultation and then submit a planning application by the end of September ’24. This will now be delayed due to the need for further design development and the need to review the project delivery approach in partnership with the Department for Education. 
 
 
Below is an indicative timeline of key activities between now and start of construction.

INDICATIVE TIMELINE TO CONSTRUCTION START

February 2024

Pre-app community consultation event 001

Spring 2024

Design evolution, further pre-application discussions with London Borough of Waltham Forest

Summer 2024

DELAYED
Second round of community consultation

Late Summer 2024

DELAYED
Planning Application Submission

Autumn 2025

DELAYED
Construction works begin

Spring 2025

DELAYED
Planning committee decision